Microelectronics Industrial Zone Regulations of Route and Opening Declarations

This regulation is made in order to promote the standardization, scientification and rationalization of Industrial Zone management, standardize the park reporting and monitor procedures. It applies to businesses construction enterprises in the region.

Reporting procedures

I. Route reporting: including official pipeline route applied by enterprises and temporary pipeline route applied by construction enterprises.

1. Applicant should apply in writing and stamp with the official seals (both user unit and construction unit).Pls report to Public Utilities Department of Microelectronics HQ and following should be clarified in application:

Purposes: the pipeline types that use route (water, electricity, gas, heat, communications, etc.), road sections route goes through, the length of route and the drawings of underground pipeline ready to use. (pls illustrate with attached drawing).

Route width: including the safe distance of different pipeline design specifications.

 

Burial depth: the depth of the center of the pipeline from surface.

Nature: marked pipeline material and stress conditions.

Permanent / temporary: is permanent or temporary occupancy of the construction route.

Recovery: propose recovery program after construction.

2. According to the relevant drawings, district planning and regulations, Public Utilities Department should audit its feasibility and reply to the applicant formally after consulting and getting permission of company leadership.

3. If approved for use, applicant needs to apply route to Construction and Transportation Bureau of Development Zone with our company opinion (Development Zone A, 4th Floor).

II. Enterprises opening reporting: including permanent one needed by company and temporary one required by construction or other reasons.

1. Applicant should apply in writing and following should be clarified in application:

(1)Reason and purpose

(2)Permanent or temporary

(3)Attached map should show opening length, width, area, specific location and underground pipeline map.

(4)For temporary construction opening, pls state time limits.

(5)Pls propose recovery program after construction.

(6)Pls report to Public Utilities Department of Microelectronics HQ after stamped with the official seals (both user unit and construction unit).

2. According to regulations, Public Utilities Department should audit its feasibility and reply to the applicant formally after consulting and getting permission of company leadership. Permanent opening needs to be applied and transacted the relevant procedures to Construction and Transportation Bureau of Development Zone with our company opinion.

The rules are formulated by the Department of Public Utilities of the TEDA Microelectronics Industrial Zone Corporation which owns the power of interpretation, since the date of issuance.

Public Utilities Department

2012-12-18

Click to download《Router Application Form of Microelectronics Industrial Zone》